On January 6, 2011, the Town of Ramapo Planning Board issued a decision granting the application for preliminary subdivision approval for the project entitled Patrick Farm Subdivision. The community at large had 30 days to file any opposition to this decision.
Please view our press release regarding the Article 78 lawsuit that was filed in the Rockland County Supreme Court opposing the January 6, 2011 Town of Ramapo approval of the Patrick Farm Preliminary Subdivision. For those of you interested in viewing the legal documents themselves we are posting the links in this update.
- The Verified Petition Complaint
- Exhibit A – Town Board of Clarkstown Resolution, 8/5/96 – Acquisition of PF for Golf Course
- Exhibit B – Town of Clarkstown buys Patrick Farm for $4.5MM on 9/3/96
- Exhibit C – 1996 Journal News Article on plan to build golf course.
- Exhibit D – Town Board of Clarkstown Resolution, 12/31/96 – Re: plans for Golf Course
- Exhibit E – Town of Clarkstown Special Town Board Meeting, 7/17/01 – Resolution to sell PF to Scenic Properties for $7.05MM
- Exhibit F – Contract of Sale from Town of Clarkstown to Scenic Development, 7/2&18/01
- Exhibit G – Minutes of Special Meeting of the Town of Ramapo, 1/25/10 – Change of zoning for PF to allow high density development.
- Exhibit H – Patrick Farm SEQR Findings Statement, 1/25/10
- Exhibit I – Preliminary Subdivision Approval, 1/10/11
- Exhibit J – Planit Main Street (ROSA Planner) Public Hearing Written Comments, 12/2/10
- Exhibit K – Town of Ramapo Department of Public Works, 7/12/10 noting unmapped wetlands.
- Exhibit L – Application for Preliminary Subdivision prepared by Leonard Jackson Associates, 8/12/10
- Exhibit M – Federick P. Clark Associate (Planner), 7/19/10
- Exhibit N – Columbia Gas Transmission, 10/28/10
- Exhibit O – Leonard Jack Associate Responses to Comments of 10/25/10 Public Hearing
- Exhibit P – Palisades Interstate Park Commission written comments 10/20/10